Change orders in construction: what they are and how to handle them in an old house

Change order construction basics for Somerville and Cambridge homeowners: why change orders happen in old houses, what to put in writing and the red flags.

Open living space during a renovation with new hardwood floors

In construction, a change order is a written, signed amendment to your contract that changes the scope, price or schedule after work is underway. In old Somerville and Cambridge houses, change orders are almost guaranteed, because nobody can see inside a 100-year-old wall until it is open.

The good news: handled in writing, change orders are routine. Below is how I explain them to clients and how Massachusetts law expects them to work.

What is a change order in construction?

Your contract describes a specific scope of work for a specific price. A change order is any agreed change to that deal, such as:

  • Added work: replacing rotted framing found during demolition.
  • Removed work: you decide to keep the existing radiators.
  • Substitutions: a different tile, window or fixture than the contract specifies.
  • Schedule changes caused by any of the above.

A change order can lower the price, too. Credits for deleted work belong on paper just like extras.

Why change orders happen in old Somerville and Cambridge houses

Many of the triple-deckers and two-families I renovate around Davis Square, Union Square and Porter Square are a century old. After that many owners, here is what I commonly find behind the plaster:

  • Old wiring, including knob-and-tube, that cannot stay once walls are open. See my knob-and-tube guide.
  • Rot and insect damage at sills, porches and under old bathrooms.
  • Lead paint. Homes built before 1978 fall under the EPA's RRP program, which requires lead-safe certified firms, and that can widen the scope of prep and cleanup. More in my lead paint guide.
  • Past "handyman" work: undersized beams, notched joists, drains with no vent.
  • Owner-driven changes: once the room is open, many clients want a niche, more outlets or a bigger window.

What Massachusetts law says about changes

For home improvement work on owner-occupied homes with one to four units, three rules matter:

  • M.G.L. c. 142A, section 2 requires the original contract to include a detailed description of work and materials, the total price and a payment schedule. That is the baseline every change is measured against.
  • Section 17 makes it a prohibited act for a contractor to depart from the plans or specifications in any material way without the owner's consent.
  • The state's Office of Consumer Affairs says, on its contract requirements page, that any modification to the original contract must be in writing and agreed to by both parties.

Bottom line: a verbal "go ahead" on the stairs is not a change order. If it changes the scope or the price, it gets written down and signed.

One more thing to know: change orders are different from allowances. An allowance is a dollar amount already in the contract for finishes you pick later, like tile or light fixtures. Going over an allowance is not a surprise extra, but I still write it up so the new total is clear.

What a good change order includes

  1. A number and date, tied to the original contract.
  2. A clear description of the change and why it is needed, ideally with photos.
  3. The price of the change, as an add or a credit.
  4. The new contract total.
  5. Any effect on the schedule, in days.
  6. How it will be paid: added to a progress payment or due at a milestone.
  7. Signatures and dates from both of us, before the work is done.
Builder's tip: Ask your contractor for a running change order log, one line per change with the running total. On a gut renovation I send it with every payment request. Nobody gets surprised at the end, and the final number on Somerville's final cost of construction affidavit matches what you actually spent.

Change order red flags

  • "We'll settle up at the end." Unpriced extras turn into a final bill you never agreed to.
  • Vague original scope. "Renovate kitchen" leaves room for endless extras. Push for detail before you sign.
  • Work done first, paperwork later. Changes should be signed before the work, except a true emergency like an active leak.
  • Pressure to pay for extras in cash or outside the contract. Under section 5, work done under a separate side agreement is not covered by the Guaranty Fund.
  • Material swaps you did not approve. That is exactly what section 17 prohibits.

Hiring an owner's representative is another way to have someone review every change order on your behalf.

Change orders often start with a thin bid. See what should be inside a contractor quote before you sign.

Allowances and price dates are where many change orders start. See how they work when material prices are moving.

Need a hand?

I price change orders in writing before we touch anything, with photos and a running total. Book a free walkthrough and I will send a written line-item budget, usually within 48 hours. I work in Somerville, Cambridge and across Greater Boston.

Frequently asked questions

What is a change order in construction?

A change order is a written, signed amendment to a construction contract that changes the scope of work, the price or the schedule after the contract is signed. It can add work, remove work or swap materials.

Does a change order have to be in writing in Massachusetts?

For home improvement contracts, the state Office of Consumer Affairs says any modification must be in writing and agreed to by both parties. M.G.L. c. 142A also bars contractors from departing from the plans in a material way without the owner's consent.

Who pays for a change order?

Usually the homeowner pays for added work they approve, and receives a credit for work that is removed. The price should be agreed and signed before the work is done.

Can a contractor charge for extra work I did not approve?

A contractor should not make material changes to the plans without your consent. Ask for a signed change order before any extra work, and keep a running log of every change and its price.

See what I do as an owner's representative and how I price work.

Read this next

  1. Hiring & PlanningMassachusetts home improvement contract requirements: what must be in writingMassachusetts home improvement contract requirements under c. 142A: required terms, notices and your 3-day right to cancel, from a Somerville builder.4 min read · Keep reading →
  2. Costs & Budgets3 quotes, 3 very different prices: what is really inside each contractor bidSame job, three bids, very different totals. A Somerville builder on what is inside a quote, why they differ and how to compare them fairly.9 min read · Keep reading →
  3. Costs & BudgetsCabinet Tariffs, Jan 1, 2027: Should You Order Before the Deadline?A 50% cabinet tariff is scheduled for Jan 1, 2027. What a builder sees on supplier invoices, how price dates and allowances work, and when ordering early is smart.8 min read · Keep reading →
  4. Kitchens, Baths & ExteriorsHow a 3D scan saves time and money before your renovation startsA Matterport scan turns your home into an exact, walk-through digital model. Here's how I use it to design, price and build with fewer surprises.3 min read · Keep reading →
  5. Hiring & PlanningWhat an owner's representative does — and when you need oneYou have plans — or a clear idea. Here's who turns them into a finished project, on budget, without you living on the job site.3 min read · Keep reading →
  6. Hiring & PlanningMassachusetts contractor deposit law: how much can a contractor ask for upfront?Massachusetts contractor deposit law in plain English: the one-third cap, the special-order exception and what a fair deposit looks like in Somerville.4 min read · Keep reading →

Have a question about your project?

Plans, a sketch or just an idea — talk to me. You'll get honest advice and a clear written budget and schedule.

Free: a 30-minute call or a walkthrough of your home.

Prefer to write? Send me your project details. I reply within one business day.