A homeowner pays the contractor, the job ends, and then a subcontractor or a supplier calls to say they were never paid. Some of them also record a paper at the registry of deeds that clouds your title. A question I hear all the time is whether that is even legal when you did nothing wrong.
The short answer is that the law lets it happen, but with limits and deadlines. This is general information, not legal advice. For your own situation, talk to a Massachusetts attorney.
Can a subcontractor really lien my house if I paid the contractor?
It can happen. A mechanic's lien is a legal claim against the property, so the sub can go after the house even though the debt is the contractor's. The rules are in M.G.L. chapter 254, which I read on malegislature.gov on November 18, 2026.
This is not rare enough to ignore. NBC10 Boston reported on November 12, 2026 on a renovation firm that had been a defendant in nearly 70 lawsuits, roughly 40 of them brought by subcontractors over unpaid work. According to the story, one couple ended up with three mechanic's liens on their property. I'm not naming anyone, and one story proves nothing about your contractor. It does show what the problem looks like.
If you want the lien basics for a contract you are ending, my post on firing a contractor covers them. This post goes deeper on the unpaid-sub case.
Who can file a lien, and what has to happen first?
A lien does not appear because someone is owed money. The statute requires specific steps, and the first one is a written contract.
| Who | What they need | Where it comes from |
|---|---|---|
| Your general contractor | A written contract with you, then a recorded notice of contract | c.254, section 2 |
| A subcontractor, supplier, equipment renter or design professional | A written contract with the contractor or with another sub, a recorded notice of contract, and actual notice to you | c.254, section 4 |
| A worker owed for personal labor | Limited to 30 days of work in the 90 days before the filing | c.254, section 1 |
For a sub, both halves matter. Section 4 says the lien arises when the notice is filed or recorded and the sub gives the owner actual notice of the filing. A paper sitting at the registry that nobody told you about is a different situation from a letter that lands on your table. Either way, don't rely on that point yourself. Ask your attorney how it applies.
How much can they claim? The cap
This is the part most owners don't know. Under section 4, a sub's lien can't exceed the amount due or to become due under the original contract as of the date the sub gives the owner notice. The amount in the sub's own notice doesn't set the limit.
A simple illustration, not a prediction. Say your contract is $60,000 and you've paid $45,000 when notice arrives. About $15,000 is still due or to become due under that contract. A sub claiming $20,000 would, as I read the statute, be capped at that remaining amount. If you had already paid ahead of the work, you'd be in a different spot, because the cap depends on what is still owed under the contract on that date. Courts decide how that works in a real case.
There is a second cap for subs further down the chain. If a sub has no direct contract with the original contractor, its lien is limited to what is due or to become due under the subcontract of the sub above it, unless it sent a written notice of identification to the original contractor by certified mail within 30 days of starting work. That notice goes to the contractor, not to you. You may never see it.
Two more things to know. A clause in your contract that tries to bar the filing of a notice of contract or to block lien enforcement is void under section 32, so you can't rely on one. And a mistake in the amount a sub claims doesn't cancel the lien unless the sub knowingly claimed more than was due (section 11).
What are the deadlines?
A lien is not forever. The deadlines are strict, and they start from events at the registry of deeds or from the last day of work. Here is how I read sections 4, 8 and 11.
| Step | Deadline (whichever of these comes first) |
|---|---|
| 1. Sub records its notice of contract (section 4) | 60 days after a notice of substantial completion is recorded, or 90 days after a notice of termination is recorded, or 90 days after the contractor (or anyone under it) last worked or supplied material |
| 2. Sub records a statement of the amount due (section 8) | 90 days after a notice of substantial completion, or 120 days after a notice of termination, or 120 days after the last day of work |
| 3. Sub starts a court case to enforce (section 11) | 90 days after that statement is filed |
If the sub misses step 2 or 3, the lien is dissolved. A sub can also dissolve its own lien by recording a signed notice (section 10). A lawyer can also tell you about other ways to dissolve a lien.
There is no single "you are safe on day X" rule, and I'd distrust anyone who gives you one. Dates depend on what was recorded and when work actually stopped.
Before the job: what to put in place
Most of the protection happens before the first payment. This is the same groundwork I describe in my guide to hiring a contractor and in the ebook How to Hire a Contractor Without Getting Burned.
- Ask in writing for a list of subs and suppliers. Names, trades and rough contract amounts. If a contractor won't tell you who is on your house, that's information.
- Use a written contract and change orders. Every sub's cap is tied to the original contract, so clear paperwork matters. See what a Massachusetts contract must contain and how change orders work.
- Keep the deposit small. A big deposit is money gone before any work exists, and the lien cap doesn't help with that. See the deposit rules.
- Check the registry of deeds. Middlesex South covers Somerville, Cambridge, Medford and Arlington, and it posts search instructions. Look up your address for a recorded notice of contract.
- Verify the license. A registered contractor is not a guarantee of anything, but start there. See how to check a license.
At every payment: pay for finished work and ask for waivers
A progress payment should match work you can see, not a date on the calendar. Walk the job before you pay. Under c.142A, section 2, no final payment can be demanded until the contract is completed to the satisfaction of the parties, which I also read on November 18, 2026.
Then ask for a lien waiver with each payment. Section 32 of chapter 254 contains a statutory form, "Partial Waiver and Subordination of Lien." It lists the original contract amount, change orders, work completed to date, retainage, previous payments and the amount now due, then waives liens through a stated date. It carves out retainage, unpaid change orders and disputed claims.
Here is the catch. Section 32 protects that form only for a person who recorded a notice of contract under section 2, which means your general contractor. It does not name subs, so ask your attorney how a sub's waiver is treated and what form to use. I found no statutory form for a final waiver in section 32, so ask your attorney what to use at the end.
Joint checks, made out to both the contractor and a supplier or sub, can help in the right place, such as a large material order. A joint check only covers that one payment, so it is not a substitute for waivers. Agree on it with the contractor in writing, and ask your attorney first.
At the end of the job: final payment and the notice of substantial completion
Don't make final payment until the work is done, the punch list is closed and you hold waivers and the up-to-date sub list. Then ask your attorney about section 2A.
Section 2A says that when work is substantially complete, the owner and contractor shall record a notice of substantial completion at the registry of deeds. The owner mails a copy by certified mail, return receipt requested, to everyone who recorded a notice of contract under section 4. Recording it starts the shorter 60-day clock for new notices of contract. It is one of the few steps an owner takes part in, and it is easy to forget. The statute has the owner and the contractor both sign and record it, so you need your contractor's cooperation.
If the contract ends early, the equivalent is the notice of termination under section 2B, which I cover in the firing post. And if the contractor has already vanished, start with what to do when a contractor ghosts.
What if a lien notice shows up?
- Don't ignore it, and don't panic. Note the date you received it and keep the envelope.
- Call a Massachusetts attorney this week. The deadlines in section 8 and section 11 run on the sub's side, but you may need to act inside them.
- Ask your contractor in writing. Say what you received, ask whether the sub was paid and ask for proof and a waiver. Keep it factual.
- Don't pay anyone twice without advice. Paying the contractor again, or the sub directly, can be right in some cases. Get advice before you do it.
- Gather your paperwork: contract, change orders, payment records, waivers, sub list and the registry record.
- Ask your attorney about your other routes. For a contractor who took money and didn't finish, that may include the Guaranty Fund, which has its own limits and rules.
Want a second set of eyes on your job?
I'm Mateus, a licensed builder in Davis Square. Since 2020 I've renovated and managed over $5 million in projects around Somerville and Greater Boston. I'm not an attorney and I can't tell you how a lien applies to you. I can help you read a contract, set up payments tied to finished work and keep the paperwork straight. Book a free walkthrough and bring your contract.
Frequently asked questions
Can a subcontractor put a lien on my house if I paid my contractor in full?
It's possible. Under M.G.L. c.254, section 4, a subcontractor or supplier with a written contract can record a notice of contract and give you actual notice. The lien is capped at the amount due or to become due under your original contract on the date you get notice, so what you had already paid matters. Whether a lien is valid in your case is a question for a Massachusetts attorney.
How much can a subcontractor claim against me?
Section 4 caps the lien at what is due or to become due under the original contract as of the date the sub gives you notice, and the amount written in the sub's notice does not set the limit. A sub with no direct contract with the original contractor is further limited to the amount due under the subcontract above it, unless it sent a notice of identification within 30 days of starting. That is a general reading, not legal advice.
How long does a subcontractor have to file a lien?
As I read chapter 254, a notice of contract has to be recorded by the earliest of 60 days after a notice of substantial completion, 90 days after a notice of termination, or 90 days after the last day of work. A statement of the amount due follows under section 8, and a court case must start within 90 days after that statement under section 11. The exact dates depend on what was recorded, so ask an attorney.
What is a lien waiver and should I ask for one?
A lien waiver is a signed statement that the person has been paid and gives up lien rights through a stated date. Section 32 of chapter 254 includes a statutory partial waiver and subordination form, and it protects that form only for persons who recorded a notice of contract under section 2. Asking for a waiver with each payment is a sensible practice, and your attorney can tell you what form to use.
How do I check whether anyone recorded a lien or notice of contract on my property?
Search your address at your county registry of deeds. Somerville, Cambridge, Medford and Arlington are in Middlesex South, which posts search instructions on its website. Look for a recorded notice of contract or a statement of amount due. If you see one, call an attorney.
What should I do if I get a lien notice?
Don't ignore it. Keep it, note the date you received it, call a Massachusetts attorney and ask your contractor in writing whether the sub was paid. Don't pay anyone a second time without advice. Collect your contract, payment records and any waivers first.
See what I do as an owner's representative and how I price work.
Read this next
Hiring & PlanningCan I fire my contractor? A Massachusetts homeowner's guide to ending a renovationThe crew still shows up, but the work is wrong or late and you want out. Here is the order to do it in, and where homeowners trip.9 min read · Keep reading →
Hiring & PlanningMassachusetts home improvement contract requirements: what must be in writingMassachusetts home improvement contract requirements under c. 142A: required terms, notices and your 3-day right to cancel, from a Somerville builder.4 min read · Keep reading →
Hiring & PlanningMassachusetts contractor deposit law: how much can a contractor ask for upfront?Massachusetts contractor deposit law in plain English: the one-third cap, the special-order exception and what a fair deposit looks like in Somerville.4 min read · Keep reading →
Hiring & PlanningContractor ghosted you? A week-by-week plan for Massachusetts homeownersDeposit paid, house half torn up, no callbacks. Here is what to do in the first 7 days and the weeks after, from a Somerville builder.9 min read · Keep reading →
Hiring & PlanningThe Massachusetts HIC Guaranty Fund: who qualifies, how much it pays and how to claimMassachusetts HIC Guaranty Fund: up to $25,000 if a registered contractor won't pay a judgment. Who qualifies and how to claim, from a Somerville builder.4 min read · Keep reading →
Hiring & PlanningHiring a contractor in Massachusetts: 8 checks before you signRegistration, licenses, the written contract, the deposit and who pulls the permit — what Massachusetts law expects, in plain English.3 min read · Keep reading →